In supply and equipment management, what is the FIRST step in the procurement process?

  • A. Keep hand receipts up to date
  • B. Establish requirements
  • C. Requisition supplies and equipment through the proper channels
  • D. Properly receive, inspect, and store required items
Correct Answer: B

Rationale: The correct answer is B: Establish requirements. In the procurement process, the initial step involves determining and establishing the requirements for the supplies and equipment needed. This step is crucial as it sets the foundation for the entire procurement process by outlining the specific needs and specifications. Choice A, 'Keep hand receipts up to date,' is not the first step but rather a later administrative task. Choice C, 'Requisition supplies and equipment through the proper channels,' comes after establishing requirements. Choice D, 'Properly receive, inspect, and store required items,' is the final step in the procurement process, focusing on the physical receipt and handling of the procured items.