How does the clinical pathway or critical pathway improve quality of care?

  • A. Lists diagnosis-specific implementations
  • B. Outlines expected progress with stated timelines
  • C. Prioritizes effective nursing diagnoses
  • D. Describes common complications
Correct Answer: B

Rationale: Critical pathways outline expected progress with stated timelines. Any deviation from those timelines is called a variance.